Sinsheimer Park parking lot solar panels under construction, majority of parking unavailable

Construction fencing is up around the entire center section of the parking lot at SLO Swim Center, adjacent to the baseball stadium, just past the SLO YMCA
Posted

A large portion of the parking area of the lot adjacent to Sinsheimer Park and the SLO Swim Center is temporarily off limits, as the City of San Luis Obispo is clearing the way to install solar panel shade structures.

Above and below are images that show the center portion of the parking lot blocked off by construction fencing.

Section of construction in parking lot closest to the baseball stadium.png
This photograph shows the area near the baseball stadium in the parking lot adjacent to Sinsheimer Park, at the SLO Swim Center, where construction to install solar panels is underway.

The project will take place in phases over several months, with portions of the lot remaining open throughout construction, affecting different parts of the 218 parking spot lot.

The image below is an aerial view KSBY News captured prior to construction beginning, on July 30, 2026.

Sinsheimer SOLAR Lot prior to construction July 30 2026.png
Aerial image of the SLO Swim Center parking lot prior to solar panel construction that began August 3, 2026.

"The first two weeks of the project will be the most impactful; that's when they're putting up the big steel columns and beams the solar gets mounted on," said Noah Maidrand, City Public Works Engineer.

The construction timeline is broken into three phases:

  • Phase 1 – August: Drilling and steel structure installation
  • Phase 2 – September: Electrical and solar panel installation on the western side, near the baseball field
  • Phase 3 – October: Electrical and solar panel installation on the eastern side, near the SLO Swim Center
SLO Swim Center is at Sinsheimer Park between the YMCA and the baseball stadium.png
SLO Swim Center is at Sinsheimer Park between the YMCA and the baseball stadium

Maidrand said the city plans to keep as much parking available as possible throughout the project.

"We'll go back and forth between opening up this side of the lot and that side of the lot to try and maximize folks' parking use while ensuring that our contractor has enough space," Maidrand said.

The timing of the project is intentional. The pool is currently at peak capacity with summer campers, regular patrons, therapy swimmers, and a full lifeguard staff. Construction is set to begin when the pool closes for its annual cleaning break.

Sinsheimer Park parking lot solar panel construction

The solar canopy project is part of the city's broader effort to reach community-wide carbon neutrality by 2035.

"The city's office of sustainability identified a large host of projects to help get us there, and this is just one of many," Maidrand said.

Similar solar installations have already been completed at other locations around San Luis Obispo, including the new parking garage, the bus depot, and Fire Station No. 1.

The solar panels at the new parking garage in downtown SLO is an example of the city sustainability efforts.png
The solar panels at the new parking garage in downtown SLO is an example of the city sustainability efforts

For regular visitors like Lisa Pimentel, who has been bringing her family to Sinsheimer Pool for years, the upgrade is welcome news.

"There are no trees, really, mature trees, to park your car under, and these cars can get so hot, and then the children come out of the pool, and they just fry in their little car seats," Pimentel said.

Pimentel said she supports the investment.

"I think it's important technology, and if the city can utilize that and keep the costs down so families can still swim here, that is wonderful," Pimentel said.

Lisa Pimentel, right, and her daughter and grandchildren are regular visitors to the SLO Swim Center.png
Lisa Pimentel, right, and her daughter and grandchildren are regular visitors to the SLO Swim Center

Visitors to Sinsheimer Park, the SLO Swim Center, and the SLO YMCA should plan for reduced parking availability and allow extra time when arriving during construction. Clear signage and on-site notifications will help guide visitors through the adjusted parking layout. The city asks drivers to watch for workers and construction vehicles in the area.

For construction updates and project status, visit www.slocity.org/parkprojects. To learn more about the city's climate action efforts and the path to carbon neutrality by 2035, visit www.slocity.org/ClimateAction.

If you have a story idea you would like to send to KSBY Reporter Jessica Roe, you can reach her directly via email at jessica.roe@ksby.com.